Skip to main content

627 CHAPEL ST HAS REACHED MID-POINT IN THE CONSTRUCTION PROGRAMME

10/11/2020

627 Chapel St will reshape the commercial landscape of Melbourne’s inner city.

Construction Update:

Despite February’s snap COVID lockdown, solid progress has continued throughout 2021.

The month of March saw a significant milestones achieved, with CitiPower completing their works to the substation and permanent power on at the main switchboard. The tower’s lift shaft has been built up to level 20 and the level 16 slab works are now complete.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The project is now visually coming to life as 40% of the tower’s external glazing has been installed.

The basement lifts have been completed with their interior finishes fitted and the internal finishes (tiling, sanitary fixtures, etc.) have been procured. The lower levels also have their internal fitouts well underway.

June will see some of the floor levels finished and ready for handover for early tenant fitout integration.

With progress continuing at this current pace, we can expect 627 Chapel Street ready for completion in late 2021.